References - Plant design and supervision of construction

Full references

  Complete list of references

Selected references

Mechanical waste treatment

2020Norske Skog Review of an existing plant concept as well as the development of several alternative plant concepts for the mechanical processing of different input qualities for feeding a stationary fluidized bed boiler with up to 160,000 t/a

Estimation of investment costs, energy requirements, exhaust air concept as well as information for the construction engineering including the logistics concept
Müllex-Umwelt-Säuberung-
GmbH
St. Margarethen/A
Creation of a concept to implement the BAT conclusions at the location in St. Margarethen
2019Mayer Recycling GmbH
St. Michael/A
Tender, site management and support for the commissioning of a commercial waste fuel processing plant for main burners & calciner material with a throughput of up to 25t/h
Oswald Hackl e.U.
Wulkaprodersdorf/A
Tender, site management and support for the commissioning of a plastic sorting plant for commercial waste with a throughput of up to 20 t/h
ecorec Slovensko s.r.o/SK
Pre-design, tender preparation, support during purchasing procedure as well as supervision of construction and management of the commissioning for the replacement of an existing RDF treatment plant with a future treatment capacity of 20 t/h
2018Oswald Hackl e.U
Wulkaprodersdorf/A
Invest and plant cost estimate

Preparation of tender documents for a mechanical sorting plant for commercial waste including recovery of recyclable materials for metals, plastic and paper

Assistance of the purchase negotiation and contract design
Mayer Recycling GmbH
St.Michael/A
Preparation of a complete facility concept for the rebuilding of the mechanical fuel and sorting plant after a fire

Development of a concept for the plant according to customer requirements and state of the art

Preparation of tener documents

Creation of a restructuring plan including presentation of a transitional operation for a temporary permit of a bridging plant after a fire according to a EIA-law waste treatment plant
Griffin Refineries Oy
Helsinki/FI
Trial operation (test run) at a waste treatment plant in Chile

Preparation of a report with improvement measures for the plant
Fortum Waste Solutions
FI
Pre-planning of a plastics recycling center for 20.000 t/a of separately collected plastic waste in Norway consisting of an automatic sorting system as well as washing and extrusion lines for flat and bodily plastic fractions
Holding Graz Services Abteilung Abfall
Graz/A
Preparation of procurement documents and purchasing negotiations for changes to logistics for the removal of waste from mechanical waste treatment plant
2017Zuser Ressourcenmanagement GmbH
Peggau/A
Approval planning according to the Waste Management Act for extension and new construction for waste depots. Approval planning according to the Waste Management Act for the reconstruction of a treatment plant after a fire.
Holding Graz Services Abteilung Abfall
Graz/A
Approval planning according to the Waste Management Act for modifications of the logistics for the removal of waste from a mechanical waste treatment plant
Oswald Hackl e.U.
Wulkaprodersdorf/A
Assistance in the rebuilding of a mechanical sorting plant after a fire. Concepts for adaptation to the state of the art as well as evaluation of possible new technologies to increase added value.
Mayer Recycling
St.Michael in der Obersteiermark/A
Digitizing several existing mechanical plants and creating detailed 3D models. Concepts for upgrading sorting machines to increase added value.
Riikinvoima W2E Andritz
Oy/FI
Project management for the construction and run of mechanical fuel treatment for a fluidized bed boiler. Acceptance and performance test of the individual machines and the entire plant. Assistance in running the plant by order of Andritz,coordination of service and maintenance work. Elaboration of maintenance concepts, support in the creation of the whole plant documenation.
2016Zuser Ressourcenmanagement GmbH
Peggau/A
Support with the processing of an official environmental inspection

Approval planning according to the Waste Management Act for changes to the types of waste and the storage concept

Approval planning according to the Waste Management Act for the construction of a waste collection center
SKAPA Recycling GmbH
Kottingbrunn/A
Preparation of permitting documents according to §74 industrial law and support of the approval procedures for the expansion of the plant of various metal waste, total capacity 20000 t/a
Loacker Recycling GmbH
Götzis/A
Preparation of permitting documents according to § 37 Waste Management Act for the change authorization of a document destruction plant
Augusta Buntmetalle GmbH
Lannach bei Graz/A
Approval documents and support of the approval procedure for the entire plant location
Ekokem Corporation/FISupporting project management and assistance during the commissioning and trial period for a splitting plant for 100,000 t/a of MSW and an automatically sorting plant for up to 10,000 t/a of separately collected packaging waste in Finland
Holding Graz Services Abfallwirtschaft
Graz/A
Concept planning and investment cost estimate for the optimization of the logistics system of the domestic waste treatment plant

Concept planning and investment cost estimate for the pre-sorting of bulky waste
Riikinvoima W2E Andritz Oy/FIImplementation of different factory acceptance tests (FAT). Logic description of the whole plant control and dry run of the control. Final and detailed plans, local site supervision and project coordination. Commissioning of the waste treatment plant.

Örtliche Bauüberwachung und Projektkoordination. Inbetriebnahme der Müllaufbereitungsanlage
2015KAB Kärntner Abfallbewirtschaftung GmbH
Klagenfurt / A
Design, approval planning according to the Waste Management Act and compilation of specifications for the construction of a mechanical sorting plant and storage facilities for commercial waste for 34,900 t/a

Design, approval planning according to the Waste Management Act for storage facilities, washing area and gas station, Waste storage concept and surface drainage for the whole site of KAB in Klagenfurt
SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Design and appoval planning according to the Waste Management Act, Preparation of tender documents according to the law and construction supervision for the reconstruction of a sorting system for packaging waste
Customer does not want to be namedDesign, tender elaboration, call for tenders, tender evaluation and support during purchase for an automatically sorting plant for up to 10,000 t/a of separately collected packaging waste in Finland
2014Andritz Oy / FIDesign, tender elaboration, call for tenders, tender evaluation, support during the purchase phase and supervision during the detail engineering phase of the suppliers for a mechanical waste treatment plant in front of a fluidized bed incinerator with an annual capacity of 145,000 tons of predominantly municipal solid waste
ecovalor
Campulung/RO
Technical support during the commissioning period of a treatment plant for solid recovered fuel in Campulung/Romania
Strabag Umweltanlagen GmbH
Dresden/D
Design planning for the mechanical treatment and substitute fuel production of a MBT for 160,000 t/a in Limassol/Cyprus
2013Andritz Energy & Environment GmbH
Basic design of a treatment plant for 75.000 t/a of waste, which should be located in front of a fluidized bed burner

Call for tenders, elaboration of the investment and operational costs and preparation of a 3D-model
AWV Hartberg/ADetailed planning, compilation of specifications and conducting of procurement procedures according to the Austrian Federal Public Procurement Law for the reconstruction of a mechanical treatment plant with a capacity of 15,000 tons/Year
2012Holcim (Slovensko) a.s.
Rohoznik/SK
Concept for a modular development of decentral waste treatment plants

Preparation of a calculation model considering different input quantities, input compositions and different plant configurations, etc

Elaboration of 3D-models and calculation of the investment and operational costs for the different plant configurations
Ekokem Oy Ab
Riihimäki/FI
Conceptual and tender design for a mechanical Pre-treatment plant for MSW, an automatic sorting plant for the separated and separately collected plastic fractions and pulper units for the separated organics and paper fractions for a site in Turku/FI

Comparison of the received offers and elaboration of a evaluation report
Saubermacher AG
Graz/A
System analysis, Compilation of specifications and handling of the procurement procedure, supervision, accompaniment of the commissioning process and acceptance of an after-treatment-plant (fine processing and sorting) for pretreated electronic scrap
Paperinkeräys Oy/FICreation of a site development concept and implementation of technical facilities for a paper sorting plant including a transfer station for biogenic waste, a sorting plant for electronic scrap and a document destruction plant with a capacity of 100,000 t/a
AWV Hartberg/AApproval project and accompaniment during the process according to the Austrian Waste Management Act for rebuilding a sorting plant for residual and packaging waste with a capacity of 12,000 t/a
Anton Mayer Ges.m.b.H
St. Michael/A
Pre-design and draft planning for the construction of a homogenization plant for substitute fuel with a capacity of 125,000 t/a
2011KAB Kärntner Abfallbewirtschaftung GmbH
Klagenfurt/A
Pre-design and draft planning, approval planning according to the Austrian Waste Management Act and compilation of specifications for the construction of a mechanical sorting plant for commercial wastes and packaging wastes with a capacity of 34,500 t/a
Ekokem Oy Ab
Riihimäki/FI
Compilation of specifications for a mechanical treatment plant destined to extract fuel and a fine fraction rich in organic substances from various waste streams; capacity of 100,000 t/a
Zuser Umweltservice GmbH
Peggau/A
Approval planning according to the Austrian Waste Management Act for several adaptions of an existing waste treatment plant with a capacity of 159,500 t/a
Gaugl Metallhandel GmbH
Tiefenbach bei Kaindorf/A
Compilation of specifications, handling of the procurement procedure, construction supervision and overall project coordination for the construction of a metal- and scrap waste treatment plant with associated secondary plants, a scrap car drainage plant, a scrap car disassembly plant and a transshipment station for various dry waste streams; overall capacity of 35,000 t/a
2010ThermoTeam Alternativbrennstoffverwertungs GmbH
Graz/A
Approval planning for various adaptations of the existing plant according to the Austrian Waste Management Act and permission for an increase in the allowed annual troughput from 90,000 t/a to 99,500 t/a
Ekokem Oy Ab
Riihimäki/FI
Pre-design planning for the construction of a mechanical treatment plant for extraction of fuel and recyclable waste material from different waste streams with a capacity of 35,000 t/a
AE&E Austrian Energy & Environment
Graz/A
Leadership of the setting-up operation and the test run of a SRF-treatment plant for the application in a fluidized bed combustion, capacity: 75 t/h in Schwedt, Germany
Saubermacher
Dienstleistungs AG
Graz/A
Compilation of specifications, handling of the award of contracts and construction supervision of a treatment plant for waste electric appliance and polluted scrap for 20,000 t/a
2009Müllex Umwelt-Säuberung GmbH
St. Margarethen an der Raab/A
Approval planning according to the Austrian Waste Management Act for several adaptions of a waste treatment plant, capacity 80,000 t/a
Saubermacher
Dienstleistungs AG
Unterpremstätten/A
Pre-design and approval planning according to the Austrian Waste Management Act, compilation of specifications, handling of the award of contracts and supervision of the construction for a treatment plant of garage wastes, capacity 15,000 t/a

Pre-design and approval planning according to the Austrian Waste Management Act for the construction of a treatment plant of electrical waste, capacity 20,000 t/a
Gaugl Metallhandel GmbH
Schönau/A
Approval planning according to the Austrian Waste Management Act for the construction of a scrap waste treatment plant incl. associated secondary plants, dissambly of old cars and a reloading station for demolition and construction waste, capacity 35,000 t/a
WKU Wiener Kommunal-Umweltschutzprojekte GmbH
Wien/A
Compilation of specifications and handling of the award of contracts for the construction of a waste logistics center for residual waste of the City Vienna, consisting of a mechanical treatment plant and a baling storage with a capacity of 2,600 t/d
2008WKU Wiener Kommunal-Umweltschutzprojekte GmbH
Wien/A
Pre-design and technical approval documents according to the Austrian Environmental Impact Assessment Act (UVP) for a waste logistic center of residual waste of the city Vienna, (consisting of a mechanical treatment plant with 130 t/h and a bale storage with capacity of 2,600 t/d)
Josef Buchhauser
Voitsberg/A
Approval planning for a waste treatment center, consisting of a reloading station, an intermediate storage and a mechanical waste sorting plant, capacity 30,000 t/a
Abfallwirtschaftsverband Lavanttal
Lavamünd/A
Compilation of specifications, handling of the award of contracts and supervison of the construction of a reloading station for wastes and a regional center for recyclable wastes
AE&E Austrian Energy & Environment
Graz/A
Pre-design for a treatment plant of solid recovered fuel (SRF) for the input into an atmospheric fluidized bed combustion, capacity 75 t/h in Leipa/Germany
in cooperation with company Envicare
2007Müllex Umwelt Säuberung GmbH
St. Margarethen an der Raab/A
Approval planning according to the Austria Waste Management Act, compilation of specifications, handling of the award of contracts and assistance in supervision for the rebuilding of a splitting plant for commercial waste , capacity 70,000 t/a
Bakonyi Erömü Részvénytáraság
Ajka/HU
Pre-design, compilation of specifications, handling of the call for tenders, award of contracts for the construction of conveyor, storage and dosing systems of solid recovered fuels of wastes for feeding a fluidized bed combustion, capacity 150,000 t/a
Fernwärme Wien GmbH
Wien/A
Approval planning for a reconstruction of the slag output system of rotary kiln, capacity 20,000 t/a
EWB Entsorgungswirtschaft am Bodensee GmbH
Lustenau/A
Pre-design, approval planning according to the Waste Management Act, compilation of specifications, handling of the call for tenders, award of contracts and supervision of construction for a sorting plant of packaging and plastic waste of commercial waste in Lustenau, capacity 42,000 t/a
2006ZUMA
BeteiligungsgesmbH & Co
Abfallstoffverwertungs KG
Wien/A
Approval planning according to the Waste Management Act for a reloading station of wastes with mechanical treatment, capacity 90,000 t/a
Hubert Häusle GmbH
Lustenau/A
Approval procedure according to the Austrian Environmental Impact Assessment Act for a waste treatment plant, capacity 150,000 t/a
Abfallwirtschaftsverband Liezen
Liezen/A
Compilation of specifications, handling of the call for tenders, award of contracts and supervision of the extension of a mechanical treatment plant, capacity 25,000 t/a
Holcim (Bulgaria) AD
Beli Izvor/BG
Pre-design, compilation of specifications, handling of the call for tenders, award of contracts and supervision of construction for a solid recovered fuel (SRF)-treatment incl. a intermediate storage and feeding into the thermal treatment process in the cement plant, capacity 20,000 t/a
Saubermacher
Dienstleistungs AG
Graz/A
Pre-design and approval planning, compilation of specifications, handling of the call for tenders, award of contracts and supervision of construction for a mechanical waste treatment plant with an automatic sorting system for packaging waste, paper and commercial waste with a capacity of 50,000 t/a
2005W&P Wietersdorfer & Peggauer
Zementwerke GmbH
Klein St. Paul/A
Detail planning of SRF-treatment plant with intermediate bunker, call for tenders and awards of contracts, capacity 55,000 t/a
WAV Betriebsführung GmbH
Wels/A
Detailplanning of SRF-treatment plant and support of choosing the process of the technical parts, capacity 100,000 t/a
Saubermacher
Dienstleistungs AG
Graz/A
Retrofitting of an existing waste splitting plant (capacity of 30,000 t/a), design work, approval planning and handling of the administrative procedure, compilation of specifications, handling of the call for tenders and the award of contracts and supervision till commencement of operations
ecorec Slovenska s.r.o.
Pezinok/SK
Reconstruction of an existing SRF-treatment plant, feasibility study, handling of the call for tenders and award of contracts, supervision, start-up, capacity 15,000 t/a
ecorec Cesko s.r.o.
Tremosnice/CZ
Reconstruction of an existing SRF-treatment plant, feasibility study, handling of the call for tenders and award of contracts, supervision, start-up
2004Zuser Umweltservice GmbH
Peggau/A
Approval planning and handling of the administrative procedure for the expansion of a waste treatment company, including a scrap wood treatment plant, SRF treatment plant as well as an operation shop and corresponding storage facilities
KAB Kärntner Abfallbewirtschaftung GmbH Klagenfurt/AApproval planning according to the Waste Management Act for a dry-mechanical waste treatment plant with a capacity of 34,900 t/a
Müllex Umweltsäuberungs GmbH
Gleisdorf/A
Compilation of specifications, handling of the call for tenders and award of contracts, supervision of construction and assistance till commencement of operations of an SRF treatment plant for 8,000 t/a
2003AVN
Dürnrohr/A
Detailed design work and comparison of several methods for an automatic container discharging facility from the train to the waste bunker of a waste incineration plant with a capacity of 300,000 t/a
Ing. Rudolf Rottner GmbH
Fischamend/A
Design work and approval planning according to the Waste Management Act, compilation of specifications relating to process engineering, handling of the EU-wide call for tenders and award of contracts, supervision of the construction of a dry-mechanical waste sorting plant including a wind screening plant in order to derive the high caloric light fraction, capacity of 27,000 t/a of commercial and household waste
ThermoTeam GmbH
Retznei/A
Compilation of specifications relating to process engineering, handling of the EU-wide call for tenders and award of contracts, supervision of construction and assistance till commencement of operations of a treatment plant for SRF for use in the cement industry, capacity of 55,000 t/a (licensed for 90,000 t/a)
Freudenthaler AG
Inzing/A
Design work and approval planning according to the Waste Management Act, compilation of specifications relating to process engineering, handling of the call for tenders and award of contracts and supervision of the construction of a dry-mechanical waste sorting plant including a wind screening plant in order to derive the high caloric light fraction, capacity of 17,000 t/a of commercial and household waste
2002UEG Umwelt- und
Entsorgungstechnik AG
Neuseiersberg/A
Design work and handling of the administrative procedure, compilation of specifications and handling of the award of contracts for the “Recycling Center Eisenerz” featuring a dry-mechanical treatment plant for 40,000 t/a of pre-treated commercial waste and 30,000 t/a of shredder waste (light fraction) in order to derive the high caloric as well as the disposable light fractions
Müllex Umweltsäuberungs-Ges.m.b.H.
Pirching/A
Compilation of specifications and handling of the award of contracts, project management and supervision of the construction of a mechanical waste treatment plant for 30,000 t/a
2001Saubermacher
Dienstleistungs AG
Graz/A
Approval planning for an SRF treatment plant for plastic waste, capacity of 8,000 t/a
Amand Umwelttechnik Lockwitz
Dresden/D
Approval planning and detailed design work for an SRF treatment plant for 100,000 t/a
Zuser Umweltservice GmbH
Peggau/A
Approval planning pursuant to the Waste Management Act for a plant location handling 150,000 t/a
ThermoTeam
Alternativbrennstoffverwertungs GmbH
Ehrenhausen/A
Approval planning for an SRF treatment plant for 90,000 t/a including the design of the necessary logistic facilities for the removal of the produced SRF
2000Müllex Umweltsäuberungs-Ges.m.b.H.
Pirching/A
Approval planning for a dry-mechanical waste treatment plant with a capacity of 50,000 t/a and integration of existing facilities on a new operating site
ZUMA Abfallstoffverwertung
Wien/A
Pre-project including the economic evaluation of a commercial waste sorting plant for 30,000 t/a
1999Planungsgemeinschaft ATM - IKB
Innsbruck/A
Design of an SRF treatment plant for 100,000 t/a
Keske Entsorgung GmbH
Braunschweig/D
Handling of the licensing procedure for a reloading station and a recycling center for 120,000 t/a of commercial waste
Lobbe MTU GmbH
Tirol/A
Handling of the licensing procedure for the construction of a residual waste treatment plant with a capacity of 30,000 t/a
1998Amand Umwelttechnik
Lockwitz GmbH/D
Design of a mechanical residual waste treatment plant including the thermal utilization of the high caloric fraction, 85,000 t/a
Koronis S.A. - Envitec für die
Stadt Athen/GR
Basic and detailed engineering of the RDF treatment and the heavy fraction for the composting of a residual-waste-splitting plant (1,200 t/d) for the region Attika (Athens)
Lobbe MTU GmbH
Tirol/A
Concept for construction of a residual-waste-splitting-plant
Prazské Sluzby a.s., Praha/CZEngineering of a sorting plant for packaging waste for the city Praha (25,000 t/a)
1997Stadtreinigung Dresden GmbH/DDraft engineering of a mechanical residual waste treatment plant at the Radeburger Straße landfill
Georg Katzlberger
Ges.m.b.H. & Co. KG
Mettmach/A
Approval planning according to §29 AWG for a sorting plant
Kröpfel Ges.m.b.H.
Attnang-Puchheim/A
Adaptation and expansion of existing plants to a residual waste splitting plant
RSA GmbH Marienberg/DApproval planning for a mixed plastic waste sorting plant
1996Austrian Energy & Environment
Graz/A
Consultative work and design of the fuel supply system and the intermediate storage in a fluidized – bed boiler (100 MW) for the light fraction
Loacker Recycling GmbH
Götzis/A
Approval planning for a waste management centre
Vorwagner GesmbH & CoKG
Pinsdorf/A
Approval planning for a sorting plant according to § 29 of the Waste Management Act
1995AVL Abfallverwertungsges
des Landkreis Ludwigsburg mbH
Bietingheim-Bissingen/D
Draft engineering for a thermal treatment facility for the light fraction (40 MW)
AWE GmbH
Dohna bei Dresden/D
Draft engineering for a plant using the „residual waste splitting-system“ (35,000 t/a), conditioning, Rott, thermal treatment of the light fraction in a paper factory
Saubermacher
Süd d.o.o.
Murska Sobota/Slovenien
Design of a waste treatment plant and several waste collection centers for the Region of Celje/Slovenia
1994ABRG Abfallbehandlungs- und Recycling GmbH
Arnoldstein/A
Design work and logistic concept for the storage and treatment of anorganic waste in Arnoldstein
Grüne Tonne Neunkirchen Ges.m.b.H./AExpansion of an existing sorting plant for dry waste
Granuplast
Kunststoffverwertung GmbH
Wien/A
Project management and supervision of construction of a plastic recycling plant (15,000 Mg/a)
1993ard-Asphalt Recycling GmbH
Dresden/D
Engineering of a half-mobile sorting plant for demolition waste (performance: 30,000 t/a) in Dresden
ARGE Leithäusl-Katzlberger
Mehrnbach, Mettmach/A
Engineering of a sorting plant for packaging material
ARW Altstoffrecycling Wien GmbH/AEngineering of a sorting plant for commercial and building waste (40,000 t/a) in Vienna
Welser Abfallverwertung Ges.m.b.H
Wels/A
Design of a sorting plant for commercial waste and packaging waste as well as of a shredder plant for residual waste with a capacity of 30,000 t/a
1992abr Asphalt-Beton-Recycling GmbH
Riesa/D
Engineering of a waste management center including facilities for industrial waste sorting, demolition waste processing, mixed construction waste sorting, used lumber size reduction, sewage sludge drying, power/heat generation, contaminated soil scrubbing at Riesa/Saxony
BWG Weiz Baustoff-Wiederverwertungs Ges.m.b.H.
Unterpremstätten/A
Engineering of an industrial waste sorting facility (8,500 t/a) for the district of Weiz, Styria
Landratsamt Garmisch-Partenkirchen/DEngineering of an industrial waste sorting and mixed construction waste treatment plant (19,000 t/a) for the rural district of Garmisch Partenkirchen/G
Hettegger Sepp & Söhne
Transportunternehmen KG
Schwarzbach in Pongau/A
Engineering of an industrial waste sorting plant and bulky and residual waste treatment facility (13,000 t/a)
Welser Abfallverwertung Ges.m.b.H.
Wels/A
Preliminary project for a waste management center featuring a sorting plant for industrial waste, a composting plant for biogenic waste, a sorting plant for mixed construction site rubble, a treatment plant for demolition waste, the treatment of contaminated sites and a recycling plant for plastic waste
1991AVL Abfallverwertungsges
d. LK Ludwigsburg mbH
Bietigheim-Bissingen/D
Engineering of a recycling park including sorting plants for commercial waste, DSD-light fraction and plastics processing at Benningen
Kurz Recycling GmbH
Schwaigern/D
Engineering of an industrial waste sorting plant (12,000 t/a) at Schwaigern/LKR Heilbronn
Amt der Oö Landesregierung/AEngineering of a sorting plant (14,000 t/a) handling plastics from recycling yards
O.Ö. Landes-Abfallverwertungsunternehmen
Ges. m.b.H./A
Engineering of a central storehouse with sorting plant and plastics processing plant for material from approx. 100 recycling yards
1990Burgenländischer Müllverband
Oberpullendorf/A
Detail engineering for the reconstruction of all transfer stations
Landratsamt Garmisch Partenkirchen/DEngineering of recycling yards at Murnau, Mittenwald and Oberammergau

Preliminary project planning for a commercial waste sorting plant at Eschenhohe
GWV Gesellschaft für
Wertstoffverwertung mbH
Remseck/D
Engineering of a processing plant for commercial waste, collected materials, demolition waste and mixed construction waste at Remseck
NGV Nürnberger Gewerbemüll
Verwertung GmbH & Co KG/D
Design of a commercial waste sorting plant (100,000 t/a)
Toifelhart Ges.m.b.H.
Wien/A
Design of a processing plant for demolition waste, mixed construction site rubble and leaf and yard wastes (120,000 t/a) in Simmering
1989AEVG Abfall-Entsorgungs- u.
Verwertungs Ges.m.b.H.
Graz/A
Design work for an industrial waste sorting plant (16,000 t/a)
CANURO für Waste Management Inc.
USA
Engineering of a commercial waste sorting plant (2,200 t/a) for Sunnyvale (California, U.S.A.)

Engineering of a sorting plant handling (400 t/a) for Oakland/Michigan, U.S.A.
Hubert Häusle Ges.m.b.H.Design of a commercial waste sorting plant (35,000 t/a)
Schlager Ges.m.b.H.
Graz/A
Engineering of a commercial waste sorting plant for 8,000 t/a

back to top

Biologische Abfallbehandlung (Kompostierung, MBA)

2019Biogas ZEMKA GmbH
Zell am See/A
Submission project according to the law for increasing thecapacity of the biogas plant
in collaboration with Machowetz & Partner Consulting Ziviltechniker GmbH
2018Fuchsluger GmbH
Aschbach/A
Pre-planning and preparation of approval documents according the Waste Treatment Act for a composting plant with a capacity of 9.985 t/a
BRM Recycling GmbH
A
Re-planning for a composting plant with a capacity of 18.000 t/a
2017Servus Abfall Dienstleistungs GmbH & CoKG
Graz/A
Approval planning and preparation of specifications for the rebuilding of plant components of a MBT in Frohnleiten after a fire, capacity 93,700 t/a
2016Servus Abfall Dienstleistungs GmbH & CoKG
Graz/A
Approval planning and compilation of specifications for the installation of a dosing bin in the MBT Frohnleiten, capacity 93,700 t/a
SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Preliminary planning and cost estimate for waste gas scrubbing to eliminate ammonia from exhaust air of the mechanical biological composting
Steirische Umweltservice GmbH
St.Lorenzen im Mürztal/A
Assistance during an official environmental inspection
Approval planning according to the Waste Management Act for modifications of a composting plant wit a capacity of 10000 t/a
2015Montanuniversität Leoben
Leoben/A
Elaboration of measures for the extension of a mechanical-biological waste treatment plant in Croatia, capacity 72,000 t/a
2014Stockerauer Saubermacher GmbH
Stockerau/A
Site investigation for the construction of a compost plant
2013Holcim (Hrvatska) d.o.o.
Koromacno/CRO
Support for the clarification of possible technical adjustments of a mechanical-biological waste treatment plant to achieve the requested fuel quantities
Servus Abfall
Dienstleistungs GmbH & CoKG
Graz/A
Approval planning according to the Waste Management Act, compilation of specifications, tendering and procurement procedures according the Austrian trade law, construction supervision and commissioning of the reconstruction of the MBA Frohnleiten with a capacity of 76,000 t/a
2012Abfallwirtschaftsverband Hartberg
Hartberg/A
Support for the optimization of a composting at the MBA Hartberg
Servus Abfall
Dienstleistungs GmbH & CoKG
Graz/A
Preplanning for the reconstruction of the MBA Frohnleiten with a capacity of 76,000 t/a
Kapazität 76.000 t/a
Saubermacher Dienstleistungs AG
Wien/A
Support at the conception of a composting plant with a capacity of 10,000 t/a
2011Ragn-Sells AS
Tallinn/EE
Supervision of the construction of a mechanical biological waste treatment plant in Tallinn/Estland with a capacity of 88,500 t/a
Ekokem Oy Ab
Riihimäki/FI
Compilation of specifications for the fermentation of a fine fraction rich in organic substances gained from residental waste; capacity of 35,000 t/a;
jointly with EnviCare
Saubermacher
Slovenija d.o.o.
Murska Sobota/SLO
Analysis of possiblities for the construction of a biological treatment plant for the high organic-content fraction from domestic waste with a capacity of 30,000 t/a;
jointly with EnviCare
SAB Salzburger Abfallbeseitigung
GmbH, Bergheim/A
Pre-design, approval planning according to the Waste Management Act, compilation of specifications, tendering and procurement procedures according the Austrian trade law, construction supervision and commissioning of the conversion of Lane 3 of the mechanical biological residual waste treatment plant with an overall capacity of 154,000 t/a
2010Ragn-Sells AS
Tallinn/Estonia
Verification of implementation planning of a supplier for the construction of a mechanical biological waste treatment plant in Tallinn/Estonia with a capacity of 80,000 t/a
Saubermacher
Dienstleistungs AG
Graz/A
Verification of implementation planning of a supplier for the construction of a mechanical biological waste treatment plant in Varna/Bulgaria with a capacity of 140,000 t/a
2009Abfallwirtschaftsverband Liezen
Liezen/A
Pre-design, draft planning, compilation of specification and handling of the award of contracts of an extension of the conveying system with the capacity of 16 t/h of a mechanical-biological waste treatment plant
2008ZEMKA Ges.m.b.H.
Zell am See/A
Pre-design and approval planning according to the Austrian Waste Management Act, compilation of specification and handling of the EU-wide call for tenders and construction supervision for an upgrading of the mechanical treatment of the mechanical-biological waste treatment plant of the company ZEMKA, capacity 61,300 t/a
2007Abfallwirtschaftsverband Liezen
Liezen/A
Approval planning according to the Waste Management Act for a mechanical biological waste treatment plant with a capacity 25,000 t/a and a composting plant with a capacity 6,000 t/a
RSVG Reststoffvertriebs GmbH
Eisenerz/A
Pre-design and approval planning according to Waste Management Act for the upgrading of a biological waste treatment plant according to the state of the art
2005Abfallwirtschaftsverband Liezen
Liezen/A
Pre-design and approval planning according to the Waste Management Act, compilation of specifications, handling of the call for tenders and construction supervision for an upgrading of an existing mechanical-biological waste treatment plant with secondary shredder, capacity 14 t/h
Servus Abfall
Dienstleistungs GmbH & Co KG
Graz/A
Final approval procedure according to the Austrian law of environmental impact assessment of the mechanical-biological waste treatment plant Frohnleiten, capacity 65,000 t/a
UEG International Holding GmbH
Neuseiersberg/A
Pre-design, compilation of specifications, handling of the call for tenders and award of contracts of an anaerobic fermentation plant on Corfu/Greek for 90,000 t/a municipal waste, 5,000 t/a sewage sludge, 20,000 t/a of olive marc and other waste
2004Servus Abfall
Dienstleistungs GmbH&CoKG
Graz/A
Design of a mechanical-biological waste treatment plant with a capacity of 17,000 t/a in Lavant/East Tyrol
SAB Salzburger
Abfallbeseitigung GmbH
Bergheim/A
Compilation of specifications relating to conveyor facilities, handling of the EU-wide call for tenders and award of contracts, supervision of construction and assistance till commencement of operations of a mechanical-biological residual waste treatment plant with a capacity of 154,000 t/a
2003Servus Abfall
Dienstleistungs GmbH&CoKG
Graz/A
Compilation of specifications, handling of the call for tenders and award of contracts, project management and supervision of the construction of a mechanical biological residual waste treatment plant for 65,000 t/a
Abfallwirtschaftsverband Liezen
Liezen/A
Design work and approval planning according to the Waste Management Act, compilation of specifications relating to process engineering, handling of the EU-wide call for tenders and award of contracts, supervision of the construction of a mechanical-biological residual waste treatment plant for 25,000 t/a and a bio waste composting plant for 6,000 t/a;
In cooperation with Dr. Schippinger & Partner and Envicare
2002SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Design work and approval planning according to the Waste Management Act for a mechanical-biological residual waste treatment plant with a capacity 154,000 t/a
Georg Katzlberger
GesmbH & Co KG
Mettmach/A
Pre-design for a mechanical-biological residual waste treatment plant for 25,000 t/a
2001NUA Niederösterreichische Umweltschutzanstalt / AVN Abfallverwertung Nö Ges.m.b.H.
Maria Enzersdorf/A
Pre-design of several methods concerning the mechanical-biological treatment of residual waste
Gemeindebetriebe Frohnleiten GmbH
Frohnleiten/A
Design work and handling of a licensing procedure pursuant to the Environmental Impact Assessment Act for a mechanical-biological residual waste treatment plant with a capacity of 97,500 t/a
2000Saubermacher Süd
Murska Sobota/SLO
Pre-project for a mechanical-biological treatment plant for household waste, industrial waste and bulky waste with a capacity of 67,000 t/a
AVG Steirische Abfallverwertungs G.m.b.H.
Graz/A
Pre-engineering for a biological residual waste treatment plant for 36,000 t/a
1999Koronis - Envitec S.A. für die Region Attika/GRRDF treatment and composting of the heavy fraction for the residual-waste splitting plant (1,200 t/day) for the region of Attika (Athens); basic and detailed design work
RSVG Reststoffvertriebs GmbH
Ohlsdorf/A
Design work and assistance in the award of contracts for an exhaust air registration and treatment system in a composting plant
Zellinger GmbH
Walding/A
Pre-design of a mechanical-biological residual waste treatment plant
1998GEMES GmbH
Unterwellenborn/D
Pre-design, detail engineering, tendering, management until commencement of operations on a composting plant for 80,000 t/a
1997AEVG Abfall-Entsorgungs- u. Verarbeitungs Ges.m.b.H, Graz/AInstallation of a bio-waste treatment unit in an existing plant

Design of a yard trimmings crushing plant

Expansion of the delivery position for private cars
GEMES GmbH
Schöngleina/D
Detail engineering, tendering, management until commencement of operations on a composting plant for 60,000 t/a
1996Stadt Chemnitz, Chemnitz/DBasic research, preliminary and draft planning of a mechanic-biological plant at the Weißer Weg landfill for 80,000 t/a
GEMES GmbH
Schöngleina/D
Engineering of a composting plant (treatment and intensive - rott) using the Rott - filter process
1994ISEO Restmüll GmbH
Bretten/D
Engineering of a conditioning and rotting facility (35,000 t/a) using the „RESIDUAL WASTE - SPLITTING - METHOD“
AWV Schladming, Schladming/AEngineering and supervision of the expansion of a waste-sludge-composting plant
1993GWV Gesellschaft für
Wertstoffverwertung mbH
Remseck/D
Engineering of the enlargement of a biowaste-composting plant using the rott-filter-process in Korntal-Münchingen, district of Ludwigsburg (performance: up to 6,500 t/a)
jointly with AWIPLAN
1992Bezirksabfallverband Freistadt/AEngineering of a residual waste treatment and rotting facility (7,000 t/a) for the district of Freistadt/Upper Austria
In cooperation with Ziv.Ing. J.Ringhofer
Saubermacher
Dienstleistungs GmbH
Graz/A
Engineering of a composting plant using the Rott-filter process for 1,200 t/a bio waste in Lannach/Styria

Engineering of a composting plant (4,000 t/a) for bio waste using the Rott - filter process in Voitsberg
1991Stadtwerke Fürstenfeld Ges.m.b.H./AEngineering of a bio-waste composting facility (1,100 t/a) using the rott-filter process at Fürstenfeld/Styria
GWV Gesellschaft für Wertstoffverwertung mbH
Remseck/D
Engineering of a bio-waste composting plant (4,000 t/a) using the rott-filter process at Korntal-Münchingen
Müllex Umwelt- und Säuberungs
Ges.m.b.H.+Co KG
Markt Hartmannsdorf/A
Engineering of a bio-waste composting plant (1,500 t/a) using the rott-filter process at Markt Hartmannsdorf/Styria
1990GWV Gesellschaft für Wertstoffverwertung mbH
Remseck/D
Engineering of a composting plant for the rural district of Ludwigsburg (6,000 t/a) in Marbach
Abfallverband Kaiserwinkl
Kössen/A
Engineering of a composting plant unsing the Rott-Filter-Process for 800 Mg/a of biological waste
Schauerhuber Ges.m.b.H.
Absdorf/A
Engineering of a mobile composting plant using the Rott - Filter Process for biological waste
1989Austria Systemmüll Gesellschaft m.b.H.
Wien/A
Design work for a standard dry waste processing plant and a composting plant for organic waste
City of Guelph/CANDesign of a dry waste sorting plant and a composting plant for BIO-BIN material (100,000 t/a)
In cooperation with R.Cave & Ass. Ltd.
Toifelhart Ges.m.b.H.
Wien/A
Engineering of a compost plant refuse from cemeteries and biological waste from separate collections (50,000 t/a)

back to top

Abfalllager und Deponien (Zwischenlager für nicht gefährliche und gefährliche Abfälle, Deponie)

2019Gaßner Mülltransport GmbH
Uttendorf/A
Submission project according to the law for a storage concept and a recycling yard for waste and problematic materials
Franz Koch GesmbH
Voitsberg/A
Creation of submission documents for the expansion of an interim storage for hazardous and non-hazardous waste and a reloading station Support of the official procedures until notification
2018Entsorgungs-Service GmbH
Krems/A
Preparation of documents according Seveso III directive for a chemical-physical treatment plant for organic waste (CPO) and an interim storage facility for hazardous waste
Stadtgemeinde Deutschlandsberg
Deutschlandsberg/A
Preparation of approval documents for a recycling and hazardous waste collection center with troughput of 9.000 t/a
2017Abfallwirtschaftsverband
Neunkirchen/A
Preliminary planning and variant analysis for waste material collection centers in Neunkirchen
Stockerauer Dienstleistungs GmbH
Stockerau/A
Approval planning according to the Waste Management Act for a used material and hazardous waste collection center and a waste transfer station
2016SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Preliminary planning and cost estimation for a construction landfill wit a filling volume of 360000m3
Hans Zöchling GmbH
Hainfeld/A
Support in the administrative procedure for the classification of waste at a landfill regarding the Seveso III Directive of the EU
2015Saubermacher Dienstleistungs AG
Wien/A
Elaboration of documents in an approval process for a storage facility for hazardous and non-hazardous waste. Assessment of the classification according to Seveso III EU Directive, max. storage capacity 10,000 t
Marktgemeinde Oberalm
Oberalm/A
Design planning for the redesign of the recycling centre
2014Mürzverband
Kapfenberg / A
Design planning for the construction of a recycling center and a transfer station for residual waste, organic waste, scrap metal and scrap wood
Holding Graz Services Abteilung Abfall
Graz / A
Adaptation planning of a recycling center for the city of Graz
SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Extension of approval of an interim storage for hazardous waste (contaminated soils)
2013TGL Tauerngasleitung GmbH
Wals-Siezenheim/A
Planning a-soil excavation landfill for 500,000 m³ as part of the EIA process for the construction for the „Tauerngasleitung”
Remondis Austria GmbH Wien/AApproval planning according to the Waste Management Act for changing the capacity of hazardous waste
2012ARGE Bauschuttauffüllung und Wiederverwertung Villach/AMonitoring of a landfill containing construction waste according to the decision of the provincial government in Carinthia (in progress since 1993)
2010Remondis
Wien/A
Approval planning according to the Austrian Waste Management Act for the expansion of a storage facility for hazardous wastes
2009WSA Waste Service GmbH
Hartberg/A
Approval planning according to the Austrian Waste Management Act for the relocation and the extansion of an intermediate storage of hazardous wastes with a capacity of 16,000 t/a in Hartberg
KAB Kärntner Abfallbewirtschaftung GmbH
Klagenfurt/A
Approval planning according to the Austrian Waste Management Act for refilling of a loam pit with capacity of 103,000 m³
Mayr-Melnhof Karton Ges.m.b.H.
Hirschwang/A
Technical concept of adaption to the state of the art of the company landfill for residual materials
2008Remondis Austria GmbH
Wien/A
Pre-design and draft planning for the integration of an intermediate storage of hazardous wastes in an existing plant, storage capacity 272 t
2007WSA Waste Service GmbH
Hartberg/A
Approval planning according to the Austrian Waste Management Act for an intermediate storage and physical treatment of hazardous waste, capacity 16,000 t/a
Trans-Beton Lieferbeton GesmbH
Bruck an der Mur/A
Approval planning for the construction of an intermediate storage of high caloric value wastes in Feldbach, capacity 8,000 t
Abfallwirtschaftsverband Lavanttal
Lavamünd/A
Feasibility study for possibilities concerning the extension of the landfill Hart, approval planning according to the Waste Management Act Design of a recyclable material collection center
2006KAB Kärntner Abfallbewirtschaftung GmbH
Klagenfurt/A
Approval procedure for temporary storage facilities for hazardous waste with a capacity of 5,000 t/a
2004SAB Salzburger Abfallbeseitigung GmbH
Bergheim/A
Approval planning and handling of the administrative procedure for a mass waste landfill in order to adapt the existing landfill to the requirements of the new Landfill Act
Saubermacher
Dienstleistungs AG
Graz/A
Approval planning and handling of the administrative procedure for the construction of an intermediate storage facility with a storage capacity of 8,000 t/a
2002Georg Katzlberger
GesmbH & Co KG
Mettmach/A
Approval planning for a storage facility for hazardous waste and its physical treatment, capacity of 5,000 t/a
2001Deponie Fellach
Villach/A
Technical expert study on landfilled waste according to ALSAG-standards
O.W.R.C., Teheran/IranConsulting work and engineering for the retrofitting of the Kahrizak landfill
Studio Tedesi – Deponie Piemont
Maleo/I
Consulting work and concept for the sanitation of a landfill for domestic and commercial waste
Schlager GmbH
Graz/A
Approval planning and handling of the administrative procedure according to the Waste Management Act for a dump for construction site rubble with a capacity of 185,000 m³
2000Afvalzorg Deponie BV
Haarlem/NL
Concept, design, supervision and start-up of a landfill reclamation project by means of an aerobisation of the waste layers and emission control
1999Abfallwirtschafstverband Wolfsberg
Wolfsberg/A
Final report on landfill stabilization (relocation of the landfill at the same site)
Abfallwirtschaftsverband Chemnitz/DEvaluation of an experiment on gas extraction and overall assessment of the landfill gas situation on the landfill Markersdorf;
In cooperation with RUK

Inspection of a degassing plant and of gauging instruments in the course of an experiment on gas extraction on the landfill Markersdorf; In cooperation with RUK
1998ARGE Bauschuttauffüllung und Wiederwertung Villach/AConcept and calculation of economic efficiency to update the landfill with the latest state of the art
Abfallwirtschaftsverband Chemnitz/DExecution of the project schedule, placing, supervision and project support for the construction of an active site digestion gas collection and landfill gas extraction of the landfill Falkenau;
In cooperation with RUK
1995Landkreis Freiberg/Sachsen/DReconversion of the sanitary landfill Muldenhütte
Gerosan GmbH
Ludwigsburg/D
Detail engineering of a treatment plant to reconverse the sanitary landfill Burghof

Design of a soil mixing plant in Ludwigsburg/D
1994AVL Abfallverwertungsges.
d. LK Ludwigsburg mbH
Bietigheim-Bissingen/D
Dynamic concept to fill up the Burghof landfill

Engineering of the enlargement of the landfill mining plant at the Burghof landfill
Abfallwirtschaftsverband Schladming/AReconversion of the sanitary landfill Aich Assach/A
AVL Abfallverwertungsges.
d. Landkreis Ludwigsburg mbH
Bietigheim-Bissingen/D
Supervision of construction at the “Froschgraben” landfill for soil and demolition waste
1993Republik Österreich,
Bezirkshauptmannschaft
Wiener Neustadt/A
Concept on reclamation of “Berger” landfill site at Weikersdorf;
in cooperation with Ziv.Ing. J.Ringhofer and Dr. Meyer
1992AVL Abfallverwertungsges.
d. LK Ludwigsburg mbH
Bietigheim-Bissingen/D
Project: the implementation of a demonstration project for site remediation by excavation, sifting and sorting

back to top

Industrial facilities

2019Bage plastics GmbH
St. Marien/A
Creation of submission documents for site approval and supervision of the approval process
sauber + stark GmbH
Waidhofen a.d. Thaya/A
Creation of submission documents for site approval and supervision of the approval process
2018Bage plastics GmbH
St.Marien/A
Preparation of approval documents for the construction of a storage hall and plant modifications

Coordination of additional specialist planners and supervision of approval procedures
2017Komex Abfallentsorgungs Gesellschaft m.b.H.
Voitsberg/A
Approval planning according to commercial law for the takeover of additional waste types
bage plastics GmbH
St. Marien/A
Supervision of the administrative procedure for a plant extension. Concept for the creation of a logistics site, preparation of submission documents and support of the approval procedure.
2016Schaufler GmbH
Ybbs/A
Survey of the surface drainage at a plant for storage of scrap metal Evaluation of dewatering regarding the state-of-the-art
Wiener Hafen, GmbH & Co KG
Wien/A
Comparison of variants of conveyor systems for the trimodal bulk handling in a bulk material storage on behalf of schneider-consult Ziviltechniker GmbH
2015Greenlife Ressourcen GmbH
Hartberg/A
Approval planning according to commercial law for a
pyrolysis plant for carbonization of sewage sludge to bio-coal
OKV Kunststoff-Verwertung GmbH
Zwentendorf/A
Preparation of permitting documents for the new construction of 3 granulating plants and a baler. Supervision from approval procedure to permission
Supervision of the official procedures to change from commercial law to Waste Management Act-regime
Manfred Arzbacher Ges.m.b.H.
Schladming/A
Elaboration of a site concept, preparation of submission documents, support administrative prodeedings for the submission of a new site Storage, presorting, sorting and handling of varoius waste streames (bulk materials to hazardous waste) including all necessary structural and infrastructural facilities
2014Buchhauser GmbH
Voitsberg/A
Preparation of submission documents for the construction of a storage of hazardous waste
Montanuniversität Leoben
Leoben/A
Preparation of submission documents for the workplace permission according to law for the construction of laboratories
2013Greenlife Ressourcen GmbH
Hartberg/A
Approval planning according to the Water Rights Act for the indirect discharger of sewages of a milk processing establishment for 24,000 inhabitants
OKV Kunststoffverwertung GmbH
Zwentendorf/A
Preparation of approval documents to build and operate a granulating plant
2012Retter & Partner ZT GmbH
Krems/A
Conception to construct a feed storage section with automatic input and loading by truck, train or ship. Capacity approximately 14.000 m³
Wiener Hafen, GmbH&CoKG
Wien/A
Approval planning, compilation of specification and construction supervision for a train loading chute with conveyors to deposit salt; Throughput: 2 x 200 m³/h
Cleanaway Österreich GmbH
Wörgl/A
Elaboration of permitting documents according to the Austrian Commercial Law for plant modifications at 5 locations in Austria
2011Wiener Hafen, GmbH&CoKG
Wien/A
Pre-design and approval planning, compilation of specifications, handling of the call for tenders and the procurement procedures for a onveyor- and storage system for salt with a capacity of 20,000 m³ and a throughput capacity of 200 t/h
Retter & Partner
Krems/A
Conceptual design for the construction of a storage facility including the automatic loading and unloading onto/from ships, trains and trucks
2010ALUmelt GmbH
Eisenerz/A
Approval planning for the construction of a remelting plant for secondary aluminium and associated facilities with an overall capacity of 142,500 t/a
2008OKV Kunststoff-Verwertung GmbH
Zwentendorf/A
Approval planning according to the Austrian Commercial Law for the construction of a storage hall and adaptions of an existing operating plant
ZUMA Beteiligungs GmbH & Co
Abfallstoff-verwertungs KG
Wien/A
Pre-design and approval planning according to the Austrian Commercial Act for taking-over and storage of wastes and demolition and construction materials, capacity 197,000 t/a
INKU AG
Klosterneuburg/A
Approval planning according to the Austrian Industrial Act for the installation of a storage container for combustible liquids
2007Zuser Umweltservice GmbH
Peggau/A
Approval planning according to the Waste Management Act for the construction of wells for extinguishing water, a feeder track and a location for the operational fire brigade
2006Wiener Hafen GmbH&CoKG
Vienna/A
Pre-design and approval planning, compilation of specifications, handling of the call for tenders, award of contracts and supervision of construction for a conveying and storage system for salt with a capacity of 200 t/h
2005Peter Palecek
Stockerau/A
Approval procedure of a noise barrier
2003Schukra Berndorf GmbH
Berndorf/A
Assessment of the current administrative situation concerning licensing procedures, approval planning according to the Industrial Code and the building laws, optimization of the fire precaution plan for a plant location of the automotive industry
2002Parsons Brinckerhoff Ltd (London) / Reichhold International
Wien/A
Evaluation of the safety and eco-management and its implementation according to IPPC-standards
2000Katzlberger GesmbH & Co KG
Mettmach/A
Handling of the licensing procedure for the construction of a waste wood – fired plant with a nominal heat output of 850 KW including a flue gas cleaning system using additives
Quarzsand Ravensburg
Ravensburg/D
Licensing procedure according to the mining law for quartz sand recovery; pilot survey and approval planning
W.Hamburger AG
Pitten/A
Handling of the inspection according to § 82 b of a paper mill
Paul & Co GmbH
Breitenau/A
Handling of the inspection according to 82 b of a paper mill
1999WCI - Woodward-Clyde International
London/GB
Evaluation of the company’s environmental protection policy and safety in a company producing chemicals
Zuser Umwelttechnik GesmbH
Peggau/A
Rehabilitation concept pursuant to the Industrial Code for the adaptation of a plant location handling a capacity of 150,000 t/a
1998Stadtreinigung Dresden GmbH
Dresden/D
Licensing procedure for a waste container washing plant and a washing facility fo rbiological waste collection vehicles
P & N Kiesgewinnung GmbH
Neudorf/A
Approval with regards of water laws for wet processing of gravel

back to top